Traffic Announcements

List of Traffic Announcements
print
Pakej Location Description Duration Activity Contact View
Pakej 5 Jalan Kuari Sg Long/Jalan Hulu Langat Lane Closure for 325m length
(CH1650m to CH1975m)
9/5/2018 till 2/15/2019
9.00am to 6.00pm
Laying 1.75m dia. MS Pipe by excavation open trench method Contractor:
Jaks Sdn. Bhd.
Nurul Hasmaliza Ismail
Safety Officer : 012-9468667
Lye Fook Wah
Snr Sepervisor : 019-8519112
Pakej 5 Jalan Hulu Langat
(Infront of Petronas Pump Station)
Lane Closure for 100m length
(CH2290 to CH2390)
9/1/2018 till 1/30/2019
9.00am to 6.00pm
Laying 1.75m dia. MS Pipe by excavation open trench method and reinstatement of road pavement Contractor:
Jaks Sdn. Bhd.
Nurul Hasmaliza Ismail
Safety Officer : 012-9468667
Lye Fook Wah
Snr Sepervisor : 019-8519112
Pakej 5 Jalan Hulu Langat FT3210 Lane Closure for 370m length
(CH3400m to CH3770m)
10/09/2018 till 2/10/2019
9.00am to 6.00pm
Laying 1.75m dia. MS Pipe by excavation open trench method Contractor:
Jaks Sdn. Bhd.
Nurul Hasmaliza Ismail
Safety Officer : 012-9468667
Lye Fook Wah
Snr Sepervisor : 019-8519112
Pakej 5 Jalan Taman Lagenda Suria Lane Closure for 315m length
(CH1985m to CH2300m)
7/20/2018 till 12/24/2018
8.00am to 6.00pm
Laying 1.75m dia. MS Pipe by pipe jacking method and reinstatement of road pavement Contractor:
Jaks Sdn. Bhd.
Nurul Hasmaliza Ismail
Safety Officer : 012-9468667
Lye Fook Wah
Snr Sepervisor : 019-8519112
Pakej 5 Jln Hulu Langat-Ampang B62 Lane Closure for 275m length
(CH4875m to CH5150m)
8/21/2018 till 12/30/2018
8.00am to 6.00pm
Laying 1.75m dia. MS Pipe by excavation open trench method and reinstatement of roadside drain & guardrail Contractor:
Jaks Sdn. Bhd.
Nurul Hasmaliza Ismail
Safety Officer : 012-9468667
Lye Fook Wah
Snr Sepervisor : 019-8519112
Pakej 6 Jalan Bukit Indah Utama Lane Closure length 700m
(CH. 1600.00 to CH. 2300.00)
15/5/2016 till 25/07/2017
(8.00am to 6.00pm)
Laying 1.5mm dia. MS Pipe by excavation open trench method and reinstatement of metalled road Contractor:
Pembinaan Ikhasas-Merak
Sdn. Bhd. PIMSB
Completed
Pakej 6 Jalan Bukit Indah Utama Lane Closure (Jacking/receiving pit)
(CH. 2300.00 to CH. 2325.00)
15/5/2016 till 15/08/2017
(8.00am to 6.00pm)
Laying 1.5mm dia. MS Pipe by excavation pipe jacking method and reinstatement of metalled road for jacking and receiving pit Contractor:
Mohd. Rosley Mahamud
Project Manager: 012 679 4633
Completed
Pakej 6 Jalan Kosas Utama Lane Closure length 250m
(CH. 2325.00 to CH. 2575.00)
01/04/2017 till 23/12/2017
(8.00am to 6.00pm)
Laying 1.5mm dia. MS Pipe by excavation open trench method and reinstatement of metalled road Contractor:
Muhammad Zulhanis
(Safety Officer): 019 218 3586
Completed
Pakej 6 Jalan Kosas 2/11 Lane Closure length 10m
(CH. 2355.00 to CH. 2365.00)
01/06/2017 till 02/08/2017
(8.00am to 6.00pm)
Laying 1.5mm dia. MS Pipe by excavation open trench method and reinstatement of metalled road Completed
Pakej 6 Jalan Kosas 2 Lane Closure length 240m
(CH. 2575.00 to CH. 3200.00)
01/02/2017 till 02/08/2017
(8.00am to 6.00pm)
Laying 1.5mm dia. MS Pipe by excavation open trench method and reinstatement of metalled road Completed
Pakej 6 Jalan Kerja Ayer Lama & Lorong Kerja Air Lama 2 Lane Closure length 175m
(CH. 5850.00 to CH. 5925.00) & (CH. 6050.00 to CH. 6150.00)
1/6/2017 (To be updated) till 30/8/2017 (To be updated)
(8.00am to 6.00pm)
Laying 1.5mm dia. MS Pipe by excavation open trench method and reinstatement of metalled road
Pakej 6 Jalan Memanda 27 Lane Closure length 175m
(CH. 5375.00 to CH. 5550.00)
3/7/2018 till 3/23/2018
(8.00am to 6.00pm)
Laying 1.5mm dia. MS Pipe by excavation open trench method and reinstatement of metalled road
Pakej 6 Jalan Pimping 1 Lane Closure length 50m
(CH. 6800.00 to CH. 6950.00)
1/8/2017 (To be updated) till 30/8/2017 (To be updated)
(8.00am to 6.00pm)
Laying 1.5mm dia. MS Pipe by excavation open trench method and reinstatement of metalled road
Pakej 6 Jalan 1, Taman Sri Ukay Lane Closure length 432m
(CH. 8210.00 to CH. 8642.00)
12/18/2017 till 17/2/2018 (Partial completion)
(8.00am to 6.00pm)
Laying 1.5mm dia. MS Pipe by excavation open trench method and reinstatement of metalled road
Pakej 6 Jalan AU3/1 dan Jalan AU3/12 Lane Closure length 218m
(CH. 8867.00 to CH. 9085.00)
1/8/2017 (ditto) till 20/11/2017 (To be updated)
(8.00am to 6.00pm)
Laying 1.5mm dia. MS Pipe by excavation open trench method and reinstatement of metalled road
Pakej 6 Jalan Bunga Anggerik 1 Lane Closure length 166m
(CH. 7038.00 to CH. 7204.00)
1/9/2017 (ditto) till 13/11/2017 (ditto)
(8.00am to 6.00pm)
Laying 1.5mm dia. MS Pipe by excavation open trench method and reinstatement of metalled road
Pakej 9 Jalan 15/56, Taman Setiawangsa Entrance To P9 Site 6/1/2017 till 7/31/2018
(8.00am to 6.00pm)
Access/Exit to P9 Site Contractor:
Pembinaan Ikhasas-Merak
Sdn. Bhd. PIMSB
Site Office: 03-91075675
Project Manager: 012-8995433
Pakej 10 Jalan Desa Cheras Lane Closure length 30m
(CH. 9175 to CH. 9225)
06/02/2017 till 31/12/2017
(10.00am to 5.00pm)
Laying 2.5m dia. MS Pipe by excavation open trench method and reinstatement of metalled road Contractor:
Pembinaan Ikhasas-Merak
Sdn. Bhd. PIMSB
Site Office: 03-91075675
Project Manager: 019-2645902
Pakej 11 Jalan Kinrara 6F Lane Closure length 450 meter. Provide temporary road diversion 2-way traffic with Flagmen – (Ch. 6200 – Ch. 6350) 6/1/2018 till 9/30/2018
(8.00am to 6.00pm)
Laying 2.40m dia. MS Pipe by excavation open trench method and reinstatement of metalled road Contractor:
Pembinaan Ikhasas-Merak
Sdn. Bhd. PIMSB
Site Office: 03-91075675
Project Manager: 019-2658430
Pakej 11 Jalan Udang Kara / Jalan Puncak Jalil (PUJ 9) One lane closure length 360meter. Provide 1-way traffic stop and go controlled by Flagmen – (CH. 5300 – CH. 5450) 8/1/2018 till 9/30/2018
(8.00am to 6.00pm)
Laying 2.4m dia. MS Pipe by excavation open trench method and reinstatement of metalled road Contractor:
Pembinaan Ikhasas-Merak
Sdn. Bhd. PIMSB
Site Office: 03-91075675
Project Manager: 019-2658430
Pakej 12 Jalan Desa Cheras Lane Closure length 30m
(CH. 8825 to CH. 8855)
6/1/2017 till 6/17/2017
(9.00am to 5.00pm)
Laying 1000mm dia. MS Pipe by excavation open trench method and reinstatement of metalled road Contractor:
Pembinaan Ikhasas-Merak
Sdn. Bhd. PIMSB
Site Office: 03-91075675
Project Manager: 019-2645902
Pakej 12 Jalan Desa Cheras Lane Closure length 18m
(CH. 8825.00 to CH. 8800.00)
12/15/2017 till 1/15/2018
(8.00am to 6.00pm)
Road Works- Reinstatement works for Pipe Crossing Contractor:
Pembinaan Ikhasas-Merak
Sdn. Bhd. PIMSB
Site Office: 03-91075675
Project Manager: 012-8995433