Installation of Fluoride Crusher systems at Fluoride Plant is in progress.

Installation of Lime Dosing Pumps is in progress.

External architectural works is in progress.

Installation of architectural wall fins and louvers is in progress.

Aerial View of Water Treatment Plant

Raw Water Pipe Crossing Across Sg. Langat

Raw Water Pipe from Tunnel to Langat 2 WTP

Project History

The Langat 2 Project is for the water treatment and distribution facilities for water transferred from the Pahang-Selangor Raw Water Transfer (PSRWT) Project for an ultimate nominal treated water output capacity of 2260 Mld.

Events

We held briefings and engagements regularly with the community to keep everyone updated on the project.

Traffic Announcements

Get the latest information on road diversions or closures.